Click on a parish to change parishes. |
|
|
|
|
|
|
|
|
|
|
|
PARISH PLANNING BASELINE |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
 |
|
|
Sector
|
Project Name
|
Implemen- tation Priority
|
Recovery Value
|
Cost Estimate
|
Last Update
|
Economic and Workforce Development |
Form Parishwide Economic Development Organization |
Future |
M
|
200,000 |
04/03/2006 |
DETAILS
|
Economic and Workforce Development |
Increase Capacity of Local Government Leadership |
Future |
M
|
5,000 |
04/03/2006 |
DETAILS
|
Economic and Workforce Development |
Conduct Vocational Training Needs Assessment |
Future |
H
|
500,000 |
04/03/2006 |
DETAILS
|
Economic and Workforce Development |
Execute a Feasibility Study for Bio-fuel Crops |
Future |
H
|
100,000 |
04/03/2006 |
DETAILS
|
Economic and Workforce Development |
Expand Twin Parish Port |
Future |
H
|
11,930,000 |
04/03/2006 |
DETAILS
|
Education |
Initiate Mobile Library Service |
Future |
M
|
200,000 |
07/01/2006 |
DETAILS
|
Education |
Build Schools Free From Floods |
Future |
H
|
47,000,000 |
07/01/2006 |
DETAILS
|
Flood Protection and Coastal Restoration |
Restore Marsh by Filling Abandoned Canals |
Future |
L
|
400,000 |
07/01/2006 |
DETAILS
|
Flood Protection and Coastal Restoration |
Construct Terraces for Marsh Restoration |
Future |
M
|
4,000,000 |
07/05/2006 |
DETAILS
|
Flood Protection and Coastal Restoration |
Develop Chenier Plain Freshwater Mgmt & Allocation |
Future |
M
|
12,000,000 |
07/01/2006 |
DETAILS
|
Flood Protection and Coastal Restoration |
Develop Post-Storm Emergency Action Plan |
Future |
M
|
300,000 |
07/01/2006 |
DETAILS
|
Flood Protection and Coastal Restoration |
Restore Natural Drainage from Freshwater Basins |
Future |
M
|
6,000,000 |
07/01/2006 |
DETAILS
|
Flood Protection and Coastal Restoration |
Stabilize Freshwater Bayou Bank |
Future |
M
|
1,500,000 |
07/01/2006 |
DETAILS
|
Flood Protection and Coastal Restoration |
Stabilize Rockefeller Refuge Gulf Shoreline |
Future |
M
|
96,000,000 |
07/01/2006 |
DETAILS
|
Housing and Community Development |
Comprehensive Master Plan and Zoning Code |
Future |
H
|
150,000 |
07/01/2006 |
DETAILS
|
Public Health and Healthcare |
Needs Assmnt of S-W La. Medical Srvcs |
Future |
|
75,000 |
04/03/2006 |
DETAILS
|
Public Safety |
Construct Communications Shelter |
Future |
M
|
1,500,000 |
07/05/2006 |
DETAILS
|
Public Safety |
Restore Fire Department Coverage |
Future |
H
|
1,750,000 |
07/01/2006 |
DETAILS
|
Transportation and Infrastructure |
Develop Parish Water and Wastewater Master Plan |
Future |
L
|
150,000 |
03/20/2006 |
DETAILS
|
Transportation and Infrastructure |
Improve Magnolia Water District WTP |
Future |
L
|
1,000,000 |
03/20/2006 |
DETAILS
|
Transportation and Infrastructure |
Dredge Delcambre Canal |
Future |
H
|
12,000,000 |
04/03/2006 |
DETAILS
|
Total number of projects 21. |
|
|
This Parish Recovery Planning Tool (RPT) contains projects that were developed by Louisiana parishes in their recovery planning process. Recovery projects included in the Parish RPT are ones that directly address needs resulting from the disaster and are additional to those already planned through other programs. Higher recovery value projects are consistent with community recovery visioning and goals, focus on overall community recovery and can achieve multiple recovery benefits. Individual sources of funding must be identified and pursued and inclusion on this site is not an indication that projects will be funded. Potential funds needed are provided as estimates that have also been developed by individual parish participants. |
|
*Recovery projects are classified by the local government into one of two priority categories: “Immediate” or “Future.” Projects classified as an “Immediate” priority currently have the attention of recovery partners and implementers in an effort to expedite the project’s implementation. “Future” priority projects have yet to receive this level of attention. |
|