Click on a parish to change parishes. |
|
|
|
|
|
|
|
|
|
|
|
PARISH PLANNING BASELINE |
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
 |
|
|
Sector
|
Project Name
|
Implemen- tation Priority
|
Recovery Value
|
Cost Estimate
|
Last Update
|
Economic and Workforce Development |
Construct Port of South Louisiana DryDock Facility |
Future |
M
|
80,000,000 |
04/03/2006 |
DETAILS
|
Economic and Workforce Development |
Institute Small Business Recovery Program |
Future |
M
|
1,600,000 |
04/03/2006 |
DETAILS
|
Housing and Community Development |
Assess Housing Needs and Capacity Building |
Future |
M
|
426,250 |
04/05/2006 |
DETAILS
|
Housing and Community Development |
Initiate Land Trust and Housing Development Prog. |
Future |
M
|
9,900,000 |
04/03/2006 |
DETAILS
|
Housing and Community Development |
Update Building Code - Building Capacity |
Future |
M
|
120,000 |
04/03/2006 |
DETAILS
|
Housing and Community Development |
Update St. Charles Parish Comprehensive Plan |
Future |
M
|
150,000 |
04/02/2006 |
DETAILS
|
Public Health and Healthcare |
Assess South-Eastern La. Medical Service Needs |
Future |
|
75,000 |
03/20/2006 |
DETAILS
|
Public Health and Healthcare |
Implement Community Health Dental Program |
Future |
CI
|
1,191,816 |
07/21/2006 |
DETAILS
|
Public Health and Healthcare |
Enhance Community Behavioral Health Program |
Future |
M
|
14,849,695 |
04/05/2006 |
DETAILS
|
Public Safety |
Construct Consolidated Emergency Operations Center |
Future |
L
|
9,100,000 |
03/20/2006 |
DETAILS
|
Transportation and Infrastructure |
Establish a Regional Transit Program |
Future |
M
|
826,750 |
08/22/2006 |
DETAILS
|
Transportation and Infrastructure |
Implement LA I_I-49 South Connection |
Future |
M
|
855,686,430 |
07/06/2006 |
DETAILS
|
Transportation and Infrastructure |
Improve St. Charles Wastewater Facility |
Future |
M
|
10,295,000 |
06/30/2006 |
DETAILS
|
Transportation and Infrastructure |
Upgrade St. Charles Water Facilities |
Future |
M
|
13,263,465 |
06/30/2006 |
DETAILS
|
Total number of projects 14. |
|
|
This Parish Recovery Planning Tool (RPT) contains projects that were developed by Louisiana parishes in their recovery planning process. Recovery projects included in the Parish RPT are ones that directly address needs resulting from the disaster and are additional to those already planned through other programs. Higher recovery value projects are consistent with community recovery visioning and goals, focus on overall community recovery and can achieve multiple recovery benefits. Individual sources of funding must be identified and pursued and inclusion on this site is not an indication that projects will be funded. Potential funds needed are provided as estimates that have also been developed by individual parish participants. |
|
*Recovery projects are classified by the local government into one of two priority categories: “Immediate” or “Future.” Projects classified as an “Immediate” priority currently have the attention of recovery partners and implementers in an effort to expedite the project’s implementation. “Future” priority projects have yet to receive this level of attention. |
|
**The Recovery Value of a project is an approximation of the impact a project will have on the overall recovery of a parish based on previous recovery planning experiences. Recovery Value is not an indication of the priority or importance of the project. |
|
|
|